Construction runs late on the owner's decisions, long before the site does

The tile nobody picked holds up the order, the installer and the painting. Why projects run late on owner decisions, and how to date each one.

A light blue and purple clay tape measure, with a blank lilac tape and an orange tip, over a dark background

Construction delays usually get counted on site: the rain, the crew that didn't show up, the material that didn't arrive. Often, the delay started weeks earlier, with a finish selection left waiting on the owner. By the time the site feels the delay, the decision that caused it is long behind.

One stalled choice holds up everything after it

An open finish decision holds up the whole sequence of the build. Follow the path of a floor tile nobody picked:

  1. The owner is still torn between two options.
  2. Without a choice, the order doesn't go out.
  3. The supplier has their own lead time, which only starts counting at the order.
  4. With no tile on site, the installer moves on to another job.
  5. The baseboards, the cabinetry and the painting wait for the floor.

Nobody on site made a mistake, and the project ran late. The schedule records the delay in execution, because that's where it shows up, and the conversation with the owner ends up being about the site.

What research says about construction delays

When you look at many projects at once, the biggest causes of delay show up far from the site. In a 2024 review of 68 studies, researchers from the University of Pernambuco and the University of Minho gathered 321 causes of delay in construction projects across several countries.

The top three in the ranking:

  • late payments from the owner to the contractor;
  • frequent requests for design changes;
  • inadequate, slow or late decision-making.

None of the three starts on site. All of them pass through a desk, an email or a conversation that got put off.

Why the owner's decision takes so long

Often, the owner takes their time because they don't know that choice has a date. For someone outside construction, "pick the floor tile" sounds like a request with no rush. Add a few everyday obstacles:

  • the sample is a photo in the group chat, the quote is in an email and the drawings are a PDF somewhere else;
  • approving takes a phone call or a trip to the office, and their calendar doesn't help;
  • the question arrives on its own, without saying what's stuck while they think;
  • doubt shows up late, when they see the room almost finished and want to change it.

Chasing them every two days wears down the relationship and, just like with a team, chasing more doesn't speed up delivery. What helps is giving them everything they need to decide, along with the date when the decision turns into a delay.

Every finish decision needs a deadline

Count backwards from the project milestone. The milestone might be the key handover, the family's move-in or a store's opening day. For each pending choice:

  1. Start with the date the work needs to begin on site.
  2. Subtract the supplier's lead time.
  3. Subtract the time for quoting and ordering.
  4. What's left is the last day to choose.

Do this math at the start of the project, for every choice that depends on a supplier order: flooring, wall tile, fixtures, faucets, windows and cabinetry. Each one gets its own date, and the owner can see the calendar of their own decisions.

With that math, the question changes. Instead of "have you picked the floor yet?", the owner gets "the floor needs to be chosen by Friday, or the kitchen falls behind". They put off the first question. The second one has a date, and they understand why.

How the owner decides on time with Experto

In Experto, the owner joins as a guest on the project and approves each choice with one click, without paying for a license. Each project is a subaccount, and the owner sees only the lists opened to them and only the items for their project.

When it's time to decide, everything is in the same item:

  • What to decide: the description with the options, plus photos of the samples and the drawings attached.
  • By when: the decision deadline in Due by and the project milestone in the Key date, when the account uses that field.
  • How to approve: they complete the item and, if they want, leave a comment. The team gets Guest completed in the notifications.

Past the deadline? The item turns red in the team's list, and whoever is keeping track sees right away which decision is holding up which project. In the Organizer, you can set up a view with just the approval lists from every project and see what each owner still needs to decide. The owner can approve from anywhere, including the task app for iPhone.

Guests are free, unlimited and don't take up a seat, on every plan. The full workflow, from design to sign-off, is in the construction project management template, and the Experto for construction and architecture page shows the rest.

Frequently asked questions

What are the main causes of construction delays?

In a review of 68 studies from several countries, the three most cited causes were late payments from the owner to the contractor, frequent requests for design changes and slow or late decisions. Weather and labor also show up, further down the ranking.

How do you get the owner to decide on time?

Give each choice a deadline counted back from the project milestone, and send along everything they need to decide: options, photos, drawings and what stalls if the decision is late.

How do you avoid construction delays from design changes?

Record each approval with its date and the approved specification. Any change after that becomes a new decision, with a new deadline, and everyone sees the effect on the schedule.